September 13, 2023

Tunas Karya Kindergarten Reconstruction Advances Cianjur Earthquake Recovery

A Rp444.18 million relocation and reconstruction project is restoring safe classrooms for 39 children and two teachers after the Cianjur earthquake.

Program Information

Program Name

Relocation and Reconstruction of TK Tunas Karya

Date

July 1, 2023

Pathway

SDGs

Collaborators

Participants

39 kindergarten students - 26 in the older class and 13 in the younger class - two teachers, and families in the surrounding 420-person community.

Location

PTPN VIII Kebun Gedeh Unit, Sukamulya Village, Cugenang District, Cianjur Regency, West Java, Indonesia

Key Activities

Relocation planning; Rp444,183,000 in construction funding; local-contractor appointment; earthworks, foundations and concrete, walls, floors and tiles, doors and windows, roofing and ceilings, painting, electricity, water and sanitation; and ongoing supervision by YIIM and partners.

Expected Outcome

A safe and earthquake-resilient kindergarten, restored learning continuity for 39 children, improved teaching conditions, and stronger post-disaster recovery for families around Kebun Gedeh.

Share the word!
Post-earthquake reconstruction of Tunas Karya Kindergarten in Cianjur

Following the magnitude 5.5 earthquake that struck Cianjur in December 2022, public infrastructure and educational facilities across the affected area suffered serious damage. One of the facilities selected for relocation and reconstruction was Tunas Karya Kindergarten.

The school served communities in Sukamulya Village, including Gedeh, Pasirsapi, and Barukaso hamlets. The area was home to an estimated 147 households comprising 420 residents. Tunas Karya had two teachers and 39 pupils, with 26 children in the senior kindergarten class and 13 in the junior class.

In July 2023, Yayasan Inspirasi Indonesia Membangun (YIIM) and PT Insight Investments Management began the initial relocation and construction stage at the PTPN VIII Kebon Gedeh unit in Cianjur, West Java. The partners worked with local contractor PT Bougenville Cipta Abadi.

The program provided Rp444,183,000, including tax, based on the conditions at the post-earthquake site and the building design and budget plan agreed by the partners.

The funding covered preliminary work, soil excavation, foundations and concrete, wall construction, floors and ceramic tiles, doors and windows, roofing and ceilings, wall painting, electrical systems, and water and sanitation facilities. YIIM, its partner, and the appointed contractor supervised implementation through the organization’s established procedures.

The relocated building was designed to restore a safe place for the 39 children and their teachers to learn. It also created a community asset for families living around the PTPN VIII Kebon Gedeh area as they continued recovering from the disaster.

The program contributes to SDG 4: Quality Education by rebuilding access to appropriate early-childhood education infrastructure in a community affected by the Cianjur earthquake.

Salam Inspirasi!